Two basic construction of artificial turf solution |
Two basic construction of artificial turf solution
News Source:Wuxi Leisutan Artificial Turf Co.,Ltd -

Program a cement concrete foundation
1 Flatness: Flatness pass rate above 95%, 5 m ruler error of 3mm.
2 Slope: Centre Venue 3 ‰ -4 ‰, Turtle drainage design. Curve 8 ‰, straight 5 ‰, semi-circular area 5 ‰, the surface should be flat, smooth, to ensure drainage.
3 strength and stability: uniform solid surface, no cracks, no bad side seams straight and smooth, about 6000mm × 6000mm cut as well. Cushion compaction, density of greater than 95%, after the pressure medium mill, no significant wheel tracks, surface dust loose, wave and so on.
4 impermeable layer: new PVC thick impermeable film days in the lap should be 200mm, edge margin greater than 150mm.
5 Warranty: basic maintenance period is 21 days.
6 Location: construction and draw lines for the accuracy needed, apply firm distinctive marker lines marked each venue.
Option II, asphalt base
A flatness: foundation should have a certain strength and stability, foundation cracks and not the product caused by freezing due to uneven heaving, flatness pass rate above 95%, 3 m ruler error 3mm.
2 Slope: Transverse <1%, vertical <1 ‰, high jump area <4 ‰, the surface should be flat and smooth to ensure drainage.
3 strength and stability: the best use of free asphalt base wax, wax-containing little or bituminous material, which must be fully compacted asphalt mixture. Uniform solid surface, smooth and no cracks, no bad side pile squeeze, no pockmarked face, smooth seams smooth. Asphalt concrete surface layer of gravel diameter of 2-5mm, the oil content of 5.8-6.4%, the bonding layer of gravel particle size of 6-9mm, containing 4.6-5.8%, no weak peeling, no surface dust loose, wave and so on.