With the emergence of artificial turf, artificial turf soccer field more and more into people's lives, but to see so many beautiful artificial turf show in there, people do not know how it is laying process is what , so let's bring everyone to know about it.
(1) Before entering the construction, the foundation of flatness, slope and surface perception testing, need to make trimming measures and requirements, after reaching the requirements before entering the construction.
(2) discharge line (measurement), find the center of the site and the two semi-circle, and in accordance with the three anchor points put foot cable, set the center line and sideline intersection site, and then set the corners of the Pythagorean theorem on the site points to the exact location of the line, and then set the position of each feature point, line, and pop with ink lines or paint lines.
(3) will move into the turf field direction along the transverse edges spread out, and advance sequentially from one end to the other end of the longitudinal edges, when spread out, as far as possible the knitting on the turf white scribe lines placed into a functional position, reducing the number of cut .
(4) will be woven into the outer edge of the turf grass and failed to place the white line on the cut line position function under stand aside, if the white dash is another weave, you must cut out by hand into the corresponding function space width white draw lines.
(5) The green turf each lap seams 1cm, with a push knife cut grass cut from the central lap, so that both sides of the turf lap as compact as possible, and then pruning knife.
(6) the bottom and turned up at the seams turf, turf turned up on each side width of about 50 cm, 25 cm wide and then connected with a central seam along the turf spread the glue were brushing the turf bottom seams and connections to bring the turf with a brush brushing glue joints, gluing width of 6 cm. Connection with the squeegee evenly coated scratch in connection belt. For best bonding results, the glue sufficiently stirred before use drums or inverted several times to mix the glue. Brushing glue in the same direction, which will help drive out the air and improve the uniformity of coating and enhance adhesion. Airing: After the glue glue volatile nature, must be the glue dry for some time, until the solvent evaporation clean, avoid sticky or produce bubbling layer, affecting the quality of bonding. Open time should not be too long, so the loss of a viscous layer, resulting unglued. Be membranous layer was dry (approximately 5-25 minutes) / 25 ℃ can be bonded. Adhesion: the adhesive on both sides of the turf should be aligned with a disposable adhesive tape connection, and the need to knock real pressure to make binding moiety bonded tightly, do not move around, so as not to affect the bonding effect. If you connect with a damp turf or phenomenon, it would take a long time to dry and allowed to dry.
(7) Upon completion of the turf basic stitching, pull again set the functional lines, the exact location of the point, with a knife cut, strip cut out of the grass, the connection with the put, scratch glue, the original preparation good white grass line back, after cementation, repeatedly beat with a rubber hammer to make the connection portion close bond.
(8) When finished stitching turf pavers, turf Folding knife needs to be part of the opening, straightened butt, cut overlapping part, then cemented.
(9) All turf after bonding carding brush mower. The first pass with a brush mower lodging the audience stand up grass line comb.
(10) by 4m * 4m specifications were put points on the audience, according to different note kilograms per square meter of sand grass high quartz sand evenly spreading to within a prescribed area, with a brush mower quartz sand and spread evenly the grass line Shu Qi, and vertical and horizontal comb once.
(11) by 4m * 4m specifications were put points on the audience, according to different injection rubber kilograms per square meter high grass paving the particles evenly into the specified area, with a rubber brush mower will spread evenly Shu Qi and grass lines, and vertical and horizontal comb once.
(12) completed after filling, then brush the grass grass fiber carding machine aspect of all time.
(13) Afterwork is completed, in accordance with the quality requirements of the artificial turf surface layer can be detected and cleared, unqualified at rectification.