Artificial turf project measurement and stakeout
News Source:Wuxi Leisutan Artificial Turf Co.,Ltd -
1. Check test foundation works to eradicate the root of the debris, if uneven, he shall be promptly corrected, leveling. Construction sites shall indeed laid cleaning, cleaning the environment and to ensure the quality of construction. Design according to the rules of the program, perform measurement and stakeout.
2, the use of steel tape measure, measure around the playground equipment is not fit the scale, if inappropriate place to do corrections.
3, pavement pavement:
(1) places along the longitudinal direction of the laying nonwovens, placing direction shall be placed at 90 degrees lawn, woven between the bonding firm.
(2), according to the length and width of a standard line drawings court ruling lines, lines through self-examination is necessary after a good stick straight.
(3), according to the turf on top of the original stone tile standard non-woven fabrics, to be overlap between 3-8mm turf.
(4) the overlapping turf Kaiping together with the knife cut the seam should be less than 3mm.
(5), laying down the seam zone cut cloth, brush on the bonding glue joints, finger touch dry after the merger received strong percussion